1995 – Fort à la Corne properties staked
1996 – Diamonds discovered in first drill program
2000 – Star Kimberlite drilling program begins and is expanded
2002 – Bulk sample program begins
2003 – Shaft sinking on Star begins
2004 – Plant construction
2004 – Underground drilling begins
2004 – Processing plant fully commissioned
July 2004 – 19.67 carat diamond recovered
November 2004 – SGF listed on the TSX
March 2005 - $116 million financing – Newmont takes 9.9% SGF
May 2005 – Advanced evaluation program announced
September 2005 – Large diameter drill program begins
October 2005 – Shore and Kensington Resources complete merger
October 2005 – Shore signs voting agreement with Cameco/UEM on FALC JV
November 2005 - $120 million financing – Newmont maintains 9.9% SGF
April 2006 – Courts uphold voting agreement
April 2006 – FALC JV budget set at $43.2 million
June 2006 – Core drilling commences on Orion kimberlite cluster
September 2006 – Acquired 42.245% of JV from De Beers
September 2006 – Acquired 15.51% of JV from Cameco/UEM
September 2006 – Shore sells 40% of JV to Newmont Mining Corp. Canada
October 2006 – 3D Model defines 276 million tonnes for Star Diamond Project
March 2007 – 3D Model defines 360-400 million tonnes for Orion South
April 2007 – Star Bulk Sample Phase III complete: 70,000 tonnes recovered
June 2007 – Shore recovers largest diamonds in Saskatchewan: 49.50cts, 22.56cts
July 2007 – Construction of shaft begins on Orion South
November 2007 – Geological estimate for Orion Centre 150-167 million tonnes
November 2007 – Star Diamond evaluations completed: Increase of 26% to US$170 per carat
November 2007 – Shore completes $30 million private placement flow-through equity financing
January 2008 – Shore announces exploration budget: $106.8 million for 2008
June 2008 – Initial NI43-101 compliant Resource Estimate completed for Star
July 2008 - Technical Report released
October 2008 – Orion South Geological Model updated – EJF 20% increase
October 2008 – Orion South diamond results – 45.95 carat diamond recovered
November 2008 – Star-Orion South Diamond Project Proposal submitted to Government of Saskatchewan
November 2008 - Shore completes $12.5 million private placement flow-through equity financing
January 2009 - Shore announces 2009 budget of $17.9 million
February 2009 - Shore holds Open House meetings in local communities for EIA process
February 2009 - NI 43-101 Compliant Mineral Resource update for Star published
March 2009 - Orion South diamond results - 299.29 carat parcel
April 2009 - Final Orion South diamond results - 32.96 carat diamond recovered
August 27, 2009 - Star Diamond Project positive Pre-Feasibility study: 171 million tonne, 20 million carat Mineral Reserve
September 10, 2009 - FALC-JV NI 43-101 Mineral Resource. Orion South - indicated: 84 million tonnes and 12 million carats
September 30, 2009 - Star Diamond project Letter Agreement signed with SaskPower
October 13, 2009 - Shore Gold announces closing of $27.5 million private placement
November 20, 2009 - Star-Orion South diamond project proposal final project-specific guidelines published
|